Friday, June 30, 2006

Roof Cricket Completed!!





Wednesday, June 28, 2006

Roof Cricket Installation & Fire sprinkler





Tuesday, June 27, 2006

Roof Cricket Installation & Fire Sprinkler Rough In work





Monday, June 26, 2006

Plumbing Rouhg In Inspection Done!!

Roof Cricket work started and Exterior Plywood Installation is being progressed.
Fire Sprinkler Rough In work is in progress.
Plumbing Rough In Inspection done today.