Friday, December 09, 2005

Day 5. Demolition Work(4)

Placing the sandbags for erosion control
Two lines of Wall have been removed (took 4 hours)
Breaker crashing the Foundation of Wall
Handball Court Wall & Foundation: Tones of Rebar....

Thursday, December 08, 2005

Day 4. Demolition Work(3)

Cheching Existing Elec. Lines & Cut.

Temporary Power Pole Installation
Continue - Saw Cutting
Cutting the Trees

Wednesday, December 07, 2005

Day 3. Demolition Work (2)

Portable Restroom has been provided today.
Completed clearing Lawn.
Saw Cutting the Brick Wall
Dumping the Con'c & Asphalt to Truck.

Ready for dumping the asphalt

Tuesday, December 06, 2005

Day 2. Demoition Work (1)






1. Removal of Asphalt Pavement.


2. Removal of Concrete Slab
3. Installation of Temp. Asphalt for providing slope to walkway for vehicle (include 4" pipe inside)

Monday, December 05, 2005

Day 1. Installation of Temp. Fence




Completed installation of Temp. Fence.