Friday, June 23, 2006

Roof Inspection Done!!!

Today we have passed roof inspection and inspector was so satisfied.
We are doing the exterior sheathing for remaining area(Metal structure). Fire Sprinkler Rough In work in progress.




Thursday, June 22, 2006

Exterior Wall Nailing Completion






Today we have completed all of nailing and necessary hardware to exterior wall to get the inspection. Plumbing Self Testing has been done and also ready to get the inspection for tommorrow.

Wednesday, June 21, 2006

Exterior Sheathing Work and Roof Parapet Work





Tuesday, June 20, 2006

Plumbing Rough-In Completion, Exterior Sheathing Work

All of Plumbing Rough-In Work completed(Gas, Water, Drain).
Inspection for that will be on Thursday.
Exterior Sheathing is in progress to get the inspection for Roof Sheathing
(This is commented by inspector).






Monday, June 19, 2006

Gas Line Completed, Exterior Sheathing