Friday, February 10, 2006

Erection of Steel Structure


Vapor Barrier & Sand on Crushed Rocks


Key to the foundation of Columns for interlocking Movement





35 ton Hydro Crane was used for lifting Steel Members..

Michael, Deputy Inspector, and Yuri, CM are watching the Erecting of Steels..
Denise, PM from City of Long Beach also attended on observing Site today.

Thursday, February 09, 2006

Base Coarse(Crushed Rock) under the Slab on Grade





Laying the crushed aggregate on ground. plumbers are fixing the drains and wraping the foam around the pipe

Wednesday, February 08, 2006

Plumbing Trench - Backfill & Compaction



Slab Base material has arrived at Site
Structure Engineer, Mr. Ken Wang came and checked the site.
Mr. Yuri and he were discussing about the Structural Issues.

Tuesday, February 07, 2006

Break Time

If you feel tired and exhuasted please press the Play button to liesten to Music.


It will take a few minutes to load but once you download it and play will be fine!!!
Powered by Castpost

Formwork for Footing & Slab, Completed Underground Plumbing

Mr. Mark Maes, Inspector from City is inspecting the underground plumbing



Monday, February 06, 2006

Formwork for the Continuous Footing and Slab

Formwork is in Progress

Plumbing Work is ready to get the inspection tomorrow