Resume the demolition Work & Start Over-Excavation
After completion of Gas Pipe Rerouting & Lifeguard's Office shift, Over-excavation work of Building Foot Print has just started from today at last.
Demolition of Storage(Old Lifeguard's Office) building and Excavation work has done 50% progress today and expected to finish tomorrow.


Excavation Work is on progress



External Plywood have been installed.